Description

Unable to allocate resources from the Allocation Workbench, the allocation workbench form is getting freeze.


Steps to Reproduce:

  • Login to the Instance
  • Impersonate as User1
  • Open ORE Allocation Workbench
  • Try manually allocating 40% to the resource User2

Release or Environment

Orlando

Cause

The Properties might have been configured incorrectly due to which the code is going into an infinite loop.

In resource management properties, 'Calendar Event Duration' is set to 24 minutes. But most of the users have 8 or 8.5 hours per day in the schedule.
The hours in the schedule should be exactly divisible by 'Calendar Event Duration'.
8.5 hours / 24 minutes. = (8.5 * 60) / 24 = 21.25. (not an integer)
8.5 hours / 30 minutes = (8.5 * 60) / 30 = 17 (integer)

Resolution

Change the ‘Calendar Event Duration’ to 30 Minutes in the Resource Management Properties
Project administration -> Properties - Resource