When attempting to add a project as a sub-project, users see the following: Error: PRJXXXXXXX can not be the New Parent to <sub-project name>.

Release or Environment

All Releases

Cause

Within the intended sub-projects there is a project task with a start date before its parent's start date.

Resolution

Identify if there are sub-projects with incorrect dates. If found, ensure they fall within the parent's start and end dates.