When in Project Workbench, creating Phases in Waterfall, Agile or Test fails and an error is thrown "Project tasks can added to only waterfall phase".

Resolution

This is working as designed. This happens when the Parent Project Phase type is not "Waterfall".

We can create phases (in Agile, Waterfall or Test) only when the Parent Project is in "Waterfall" Phase type if not "Project tasks can added to only waterfall phase" error is thrown by the Business Rule 'ProjectWorkbenchPhaseValidationAndUpdate' which is against Project Task table.