Select multiple resource plan on the left, the right widget page will display loading for a long time and some time will show the result, but some times seems to be stuck in loading.

Expected Behavior

On Resource Capacity, dates taken are the earliest start date and the maximum end date from the resource plans that have been selected and are then calculated with the requested, confirmed, allocated hours for all the users in those plans.

If the duration is more, the time to calculate these values will increase and hence it takes time.

if the duration is less the performance is good, so suggested is to select plans such that the time period of these is below 2 years for better performance.