68 views

Symptoms


When viewing a Project, the Actual Cost field is set to read-only

Release


London

Cause


Out Of Box UI Policy "Mark Capex/Opex Cost Read Only if Cost Plan Of Capex/Opex Exists" will set this field to read-only when there is a cost plan associated to the project

Resolution


If the requirement is to not have the Actual Cost field set to read-only, this UI Policy can be turned off. A word of warning though. There may be some negative effects of recalculation if this is turned off. As always, we suggestkeepingp the Out Of Box configuration

Additional Information


https://docs.servicenow.com/bundle/london-it-business-management/page/product/project-portfolio-suite-with-financials/concept/c_ActualProjectCosts.html

Article Information

Last Updated:2018-10-10 07:47:43
Published:2018-10-10