Notifications

107 views

Description

Symptoms


When the percent complete on project task is updated, the percent complete on the top task remains 0; however, when viewing the history the percent complete updates but is set back to 0 after the update.

Release


Jakarta Patch 8b

Cause


A custom business rule is setting the percent complete to 0 after update.

Resolution


Deactivate the custom business rule.

 

Article Information

Last Updated:2019-08-02 21:06:41
Published:2018-09-03