Symptoms


All child task of a project tasks are in state is closed complete and percent complete is 100. The parent record moves to closed complete state, but percent complete is not rolled up.

Release


Kingston Patch 4

Cause


All of the child tasks are set as milestones and do not contribute to the percent complete on the parent.

Resolution


Ensure at least one child task is not a milestone.

 