Symptoms


When clicking the "Sprint Burndown Chart", you see the message, Insufficient data to generate a burn down chart

Release


Kingston Patch 7

Cause


The sprint records did not exist in the metric_instance table. If a record does not exist there, it will not get the required info needed for the burndown chart. The start date was earlier than the created date of the Sprint. This is why the metric_instance record was not created automatically. 

Resolution


Need to create metric_instance record manually by matching the appropriate data of the sprint.
 
Go to metric_instance.do page 
Fill the fields to match your sprint data
 
Once that is done, go ahead and submit the record. Go to the Sprint and now you should be able to see the burndown chart. 

 