Issue Summary

The Project Planning Console error below shows when trying to indent a Project Task:
 
Permission denied to perform the action

   

Most Probable Cause

This is a security constraint issue. Debugging Security ACLs is the best approach to determine the cause.
 
 
The issue can be due to the Parent Field configured as read only for Project Tasks:
 
/nav_to.do?uri=sys_dictionary.do?sys_id=c1988f976f254100af68b1109e3ee4b1%26sysparm_view=advanced
 
The write ACL /sys_security_acl.do?sys_id=377f567798e2b000673d562b24dc8cbf  can also be blocking users with the it_project_role from editing or indenting the Parent of the Project Task.

 

 

Solution Proposed

  1. Disable or customize the ACL mentioned above.
  2. Create a dictionary-override to make the parent field read-only false on the [pm_project_task] table.
 

 