If a project created in Microsoft Project 2013 with multiple tasks and relationships is imported into the Project Management application, an incorrect lag value may be inserted.

Steps to Reproduce


  1. Activate Project Management v3.
  2. Import a project with relationships created in Microsoft Project 2013 format.
    Note that a lag of 95+ days is added to the relationships. This added lag extends the start dates of the tasks.


  1. Open the project in Microsoft Project 2013.
  2. Use the File Save As menu option and save the project with the Microsoft Project 2000-2003 or Microsoft Project 2007 file format.
  3. Import the saved project into the Project Management application.

Related Problem: PRB635702

Seen In

Eureka Patch 6 Hot Fix 2
Fuji Patch 1
Fuji Patch 3
Fuji Patch 4 Hot Fix 4
Fuji Patch 6
Fuji Patch 7 Hot Fix 5
Fuji Patch 8
Geneva Patch 1
Geneva Patch 6
Helsinki Patch 0 Hot Fix 1

Fixed In

Geneva Patch 5 Hot Fix 2
Helsinki Patch 1

Associated Community Threads

There is no data to report.

Article Information

Last Updated:2017-03-14 00:55:10